Faejao Project Design services include mechanical design, dynamic analysis, brake system design, instrumentation, and control system design. The control system design included the logic development, programming (Allen Bradley SLC503), onsite commissioning, and performance testing. The control system included a supervisory system (FactoryLink) provided by others. The project is a 1.3 Km route at 1430 TPH for the transportation of iron ore consisting of one downhill with fluid coupling drive and three plant conveyors. The plant conveyors include a variable speed conveyor with integrated gate control to two plant hoppers and a reversible stacker conveyor.
Year of Construction: | 1999 |
Location: | Ferteco, Faejao, Brazil |
Length (Tail to Head): | 1.32 km |
Power: | 3,920 kW |
Capacity: | 1,430 tph |
Strength: | ST-1600 N/mm |
Speed: | 3.32 m/s |
Material: | Iron Ore |